Construction continues to move forward on the new parking lots at North Boone Middle School and Upper Elementary, with crews making significant progress despite encountering an unexpected challenge beneath the surface.
After the existing asphalt was removed, contractors discovered that portions of the underlying base soils were too unstable to properly support the new pavement. Work was temporarily paused while engineers and construction experts evaluated several stabilization options to ensure the long-term durability of the project.
The selected solution involves mixing Portland cement into the existing soils, creating a much stronger and more stable foundation capable of supporting the new parking lots for years to come. While this additional work has added time to the project, it is a necessary investment to ensure the finished parking lots meet the district's high standards for safety and longevity.
District officials appreciate the patience and understanding of students, staff, families, and community members as construction continues. These improvements will provide safer, more durable parking areas that will benefit the North Boone school community well into the future.
#NorthBoonePride